The previous construction progress

October 2006Ground-breaking ceremony
October 2006 – March 2007Set up of the construction fence around the construction site
April 2007Installation of the sewage pressure pipe at the crossroads Chausseestr. / Wöhlertstraße
October 2007 – April 2008Preparation of the excavation pit and set up of the security fence around the construction site
7. May 2008Laying of the foundation stone
May 2008The construction works start at the northern building
November 2008The construction works start at the main building
December 2009Completion of the bare brickwork at the northern building
Spring 2010Completion of the bare brickwork at the northern building
25. March 2010Topping-out ceremony
End of 2010Completion of the building shell of the northern building
End of 2011Completion of the construction works at the northern building
Spring 2012The construction works start at the Southern building